Batavia Local Schools
800 Bauer Avenue
Batavia, OH 45103
P: 513-732-2343
F: 513-732-3221
July 2016 Update
June 2016 Update
April 2016 Update_V3
April 2016 Update_V2
April 2016 Update
March 2016 Update
Public Notice Elementary Bid Package #4
Public Notice Elementary Bid Package #4
January 2016 Update
November 2015 Update
October 2015 Update
September Aerial Photographs
September 2015 Update
August 21 Aerial View
August 2015 Building Photos
Aerial Construction Site Photos - May 1, 2015
Construction Update - April 24, 2015
 2015424123528359_image.jpg

Now that the snow has stopped falling and spring is in the air, construction has started on the new Elementary School!!  Workers are currently constructing the gym walls.  If you happen to drive by to check the progress you will notice one wall has a large rectangular hole in it.  This will allow students and visitors to look into the gym from a 2nd floor hallway.  Stay tuned to for updates as work ramps up on the New Batavia Elementary!


 

Advertisement to Bid - Bid Package #3
Construction Update - November 10, 2014

 Work on the early site package for the new Elementary School is nearing completion.  Workers have graded the site, moved utilities, installed aggregate piers, and added access roads and parking lots.  The early site package should be completed in the next several weeks.  In the coming weeks bids for construction materials will be solicited and then materials will be ordered.  Work will then begin on the construction the building sometime in the Spring.

 

 
 
 
 
 
Advertisement to Bid - Bid Package #2
Advertisement to Bid - Bid Package #2 - Addendum #1
Please select link below to see Public Bid Advertisement for new Batavia Elemetary Bid Package #2 - Aggregate Piers Package - Addendum

http://filecabinet5.eschoolview.com/7BF9653E-0889-4A80-A022-67104C9ACEFC/BLSD - OFCC - Bid Package 2 - Addendum 1.pdf
Advertisement to Bid - Bid Package #2
Please select link below to see Public Bid Advertisement for new Batavia Elemetary Bid Package #2 - Aggregate Piers Package

Advertisement to Bid - Bid Package #2 - Aggregate Piers Package
October 7, 2014 - Construction site photos
Elementary School Construction Update



September 16, 2014
At the September 15th regular Board of Education Meeting the Board approved a contract with Peterson Contractors, Inc for the installation of aggregate piers at site of the new Elementary School.  The company will remove soft loose soil and replace it with columns of dense heavy rocks.  These piers will help create a stable base on which the new Elementary School can be built.  Work on the piers is expected to start within the next 30 days and take approximately 5-7 days to complete.  During the installation of the piers workers may work during daylight hours on Saturday's and Sunday's.  A picture of what the process will look like is below.






August 28, 2014
 
The site preparation for the new Elementary School is progressing nicely.  The workers have completed approximately 50% of the work which includes moving utilities and grading the construction site.  Aerial photographs taken on August 25th are below.  The photographs show how much progress has been made over the summer. 
 


August 8, 2014
 
Workers have been busy all summer preparing the site for the construction of the new Elementary School.  They have moved utilities, added a new entrance, and cleared the area where the new building will be built.
 
 
Construction Photos - August 28, 2014
Construction Photos - August 8, 2014
View text-based website